Status report for the period 2002-02-26 to 2002-03-05

Tasks that should have been finished already

Name Duration End Completed Resources Followers Status Note
Accounting Software 90.5 2002-04-16 53%      
Software Development 58.2 2002-03-27 62%   AcSo.test.alpha  
Back-End Functions 18.3 2002-03-01 95% (100%) Paul Smith, Sébastien Bono AcSo.software.gui, AcSo.deliveries.prev  

Work in progress

Name Duration End Completed Resources Status Status Note
Accounting Software 90.5 2002-04-16 53%   Work in progress  
Milestones 90.5 2002-04-16 53%   Work in progress  
Software Development 58.2 2002-03-27 62%   Work in progress  

Tasks that have been completed

Name Start End Note
Accounting Software 2002-01-16 2002-04-16  
Milestones 2002-01-16 2002-04-16  
Technology Preview 2002-03-01 2002-03-01  
Manual 2002-01-16 2002-02-26  

Upcoming new tasks

Name Start Duration Resources Note